| Blue Ridge 2009 |
|
|
|
|
Environmental
Completed Multi-plate with Erosion Control · Client: Alberta Transportation · Consulting Firm: MPA Engineering Ltd. · Cost of Project: $1.15 million. · Location: Blue Ridge, Alberta. · Date: July - October 2009 · Scope of Work: Removal of existing multi-plate structure in Tributary of Bull Creek, a fish bearing stream. Replace multi-plate bridge with new multi-plate and backfill. Traffic Accommodation Plan, Storm Water Management Plan & ECO Plan were completed. Due to the in stream nature of this project a fish capture and release was completed before the in stream work started.
Before Picture (East side of Bull Creek)
Fish Capture
Completed Detour
Multi-plate Removal
Multi-plate Backfill
Multi-plate Insertion
Head Wall Construction
Paving Completed
|